LATEST NEWS   Sabah Electricity sets six-day deadline to restore power transmission lines to Sabah’s east coast - Chairman | Former Attorney-General Tan Sri Abdul Gani Patail dies tonight - Attorney-General Mohd Dusuki | Power outage: All 42,808 candidates sitting for SPM in Sabah unaffected - State Education Director | MCMC coordinates telecommunications restoration on Sabah’s east coast with Sabah Electricity and service providers | MCMC provides Starlink satellite connectivity at 18 critical locations to ensure field teams remain connected | 

PETRA Expects Energy Demand In Peninsular Malaysia To Double To 49.8 GW By 2050

KUALA LUMPUR, Nov 26 (Bernama) -- Electricity demand in Peninsular Malaysia is projected to more than double from 22.6 gigawatts (GW) in 2027 to 49.8 GW by 2050, with a compound annual growth rate (CAGR) of around 3.5 per cent.

Quoting the Electricity Supply and Tariff Planning and Implementation Committee (JPPPET), the Ministry of Energy Transition and Water Transformation (PETRA) said the projection accounts for the data centre sector’s rapid growth, artificial intelligence (AI), electric vehicles (EV), and energy-intensive industries.

The ministry said electricity demand from the data centre sector as a percentage of total electricity demand in Peninsular Malaysia is projected to rise from 11 per cent in 2027 to 21 per cent in 2050.

Ad Banner

Meanwhile, PETRA said that nuclear energy has been identified as one of the strategic options to replace coal as a source of baseload electricity generation, alongside gas, in line with efforts to achieve net zero carbon emissions by 2050.

“The actual capacity requirements and the details of nuclear energy’s contribution to the generation mix in the Peninsular are subject to a comprehensive feasibility study being led by MyPOWER as the Nuclear Energy Programme Implementing Organisation (NEPIO).

“However, the initial scenario decided in the JPPPET Meeting No. 1/2026 projects the potential phased entry of nuclear energy by 2040, with a mix percentage of generation of two per cent, which is approximately 2.0GW, for the period up to 2050,” in a written reply published on the Parliament’s website today.

Ad Banner
Ad Banner

PETRA was responding to Datuk Ahmad Amzad Mohamed @ Hashim (PN-Kuala Terengganu) on projections of the country’s electricity demand until 2050, the role of nuclear energy in meeting that demand and the mix of the country’s electricity generation.

In a separate oral response, the ministry said that Terengganu recorded 11 projects with a capacity of 874 megawatts (MW), followed by Kelantan with nine projects (533 MW) and Perlis with five projects (124 MW) for the implementation of large-scale solar (LSS) projects from LSS 1 to LSS 5+.

Overall, the three states recorded 25 projects with a total capacity of 1,531 MW, equivalent to 25.4 per cent of the total LSS capacity of 6,028 MW.

For the Corporate Renewable Energy Supply Scheme (CRESS), PETRA said the basic principle of implementation is “willing buyer, willing seller”, and participants’ use of the grid is subject to appropriate system access charges.

“This approach is important to prevent the costs of usage and additional system requirements from being unfairly transferred to other electricity users.

“In this case, renewable energy developers (RED) can build solar farms in any state they deem suitable, and the government has not set any regulations for these companies to build solar farms in specific states or areas,” it said.

PETRA replied to Datuk Mumtaz Md Nawi (Tumpat-PN) on the government’s steps to ensure the benefits of renewable energy investment through LSS6 and CRESS are also enjoyed by states such as Kelantan, Terengganu, and Perlis.

-- BERNAMA