First Phase Of 595MW Tasik Kenyir Floating Solar Project To Be Completed In 2028

KUALA TERENGGANU, Nov 18 (Bernama) -- The first phase of the 595-megawatt (MW) Hydro Hybrid Floating Solar (HHFS) project at Tasik Kenyir, Hulu Terengganu, is expected to be completed by the third quarter of 2028, creating employment and business opportunities for the local community.

Terengganu Infrastructure, Utilities and Rural Development Committee chairman Datuk Hanafiah Mat said the project was currently in the development phase, with physical works at the site having commenced in the third quarter of this year.

He said the first phase, which is expected to take about two years to complete, would benefit the local community through job creation and business opportunities, with some of these benefits already being realised during the development phase.

Ad Banner
Ad Banner

"To ensure the participation of local industry players, one of the conditions for the project's implementation stipulates that at least 15 per cent of the total contract value must be awarded to local contractors or businesses in Terengganu, subject to their eligibility and competitiveness," he said during the question-and-answer session during the State Assembly sitting here today.

He was responding to a question from Mamad Puteh (PAS-Kuala Berang) on the latest status of the solar farm project at Tasik Kenyir and its expected operational timeline before electricity is supplied to end-users.

Hanafiah explained that the project was being implemented under the Corporate Renewable Energy Supply Scheme (CRESS), with the electricity generated to be purchased by a corporate offtaker.

Ad Banner
Ad Banner
Ad Banner

On concerns over the damaged roads leading to the project site, he acknowledged that their condition had affected the project's implementation.

However, he said an alternative route had been provided as a temporary access road to ensure that development works could continue.

He was responding to a supplementary question from Mamad on whether the unrepaired roads leading to the project site would hamper or disrupt the solar project implementation.

The HHFS project is a collaboration between TNB's power generation subsidiary, TNB Genco Sdn Bhd, and Terengganu Inc, an entity owned by the Terengganu state government.

The HHFS pilot project at the Tasik Kenyir Dam has a capacity of 100 kilowatts (kW), covering an area of 1,085 square metres and comprising 220 solar panels.

It demonstrates the significant potential of the 36,900-hectare Tasik Kenyir for floating solar development, with up to 10 per cent of its surface area capable of being utilised to generate an estimated 2,200 MW of electricity without compromising the lake's ecology.

-- BERNAMA